    Women in Agricultural Leadership

    Ongoing
    Filters:
    Date Range:
    Team Member:

    Task Progress

    20 of 35 Tasks
    57% Complete

    Budget Usage

    $156,000
    of $240,000 (65%)

    Milestone Status

    3 of 6 Completed
    2 in Progress, 1 Not Started

    Project Risk Level

    Medium Risk
    9 of 15 resolved

    Project Summary

    Empowering women in agricultural research, education, and entrepreneurship through targeted capacity building.

    Project Details

    Status:
    Ongoing
    Start Date:
    Feb 15, 2023
    End Date:
    Feb 14, 2025
    Lead Organization:
    University of Dar es Salaam
    Budget:
    $240,000

    Task Completion Trend

    Project Timeline & Upcoming Deadlines

    Key events and workload distribution

    Timeline View

    Start
    Feb 15, 2023
    Today
    May 17, 2025
    End
    Feb 14, 2025

    Upcoming Deadlines

    Implementation Phase
    Due: 2023-06-15
    702 days overdue
    Testing Phase
    Due: 2023-08-15
    641 days overdue
    Deployment
    Due: 2023-09-30
    595 days overdue

    Monthly Workload Distribution

    Lower workloadHigher workload

    Recent Activities

    Gender in Agriculture Research

    Completed
    Jun 1, 2023
    Multiple Locations

    Gender in Agriculture Research

    Completed
    Jun 1, 2023
    Multiple Locations

    Women Leadership in Agriculture Workshop

    Completed
    Apr 20, 2023
    Dar es Salaam, Tanzania

    Project Alerts

    Budget Alert
    Project is approaching budget limit (85% used)2023-06-28
    Milestone Delayed
    Testing phase is behind schedule by 5 days2023-06-25
    New Team Member
    Sarah Johnson has been added to the project team2023-06-20